Year of realization: 2003

Product: Spin SCADA

Providing Spin SCADA and its integration services to existing relays and PLCs at each end of the Botucatu – Chavantes 230-kV line, of CTEEP concession area. During the process, Spin team identified a factory defect in a protection relay of SE Botucatu. The quick solution regarding the relay firmware was only possible because of the experience of Spin professionals, who got in in contact with manufacturers abroad and showed that when occurring events in a given sequence the relay went into deadlock and rebooted.

Used products

  • Spin detected a problem in the firmware of protection relays and contacted the manufacturer to identify the error.

Download the detailed case

CTEEP 01 (232.86 KB)